A contractor undertakes to complete the construction of a tunnel 720 meters long in 240 days and employs 60 men for the purpose. After 120 days, he finds that only 240 meters of the tunnel is complete. How many more men should be employ in order to complete the work in time?

Ques:- A contractor undertakes to complete the construction of a tunnel 720 meters long in 240 days and employs 60 men for the purpose. After 120 days, he finds that only 240 meters of the tunnel is complete. How many more men should be employ in order to complete the work in time?
1 6004

One Answer on this Question

Leave a Reply

Your email address will not be published. Required fields are marked *

Scroll to top