During a given week A programer spends 1/4 of his time preparing flow chart, 3/8 of his time coding and the rest of the time in debugging the programs. If he works 48 hours during the week , how many hours did he spend debugging the program. - Just Crack Interview

During a given week A programer spends 1/4 of his time preparing flow chart, 3/8 of his time coding and the rest of the time in debugging the programs. If he works 48 hours during the week , how many hours did he spend debugging the program.

During a given week A programer spends 1/4 of his time
preparing flow chart, 3/8 of his time coding and the rest of
the time in debugging the programs. If he works 48 hours
during the week , how many hours did he spend debugging the
program.

Ques:- During a given week A programer spends 1/4 of his time preparing flow chart, 3/8 of his time coding and the rest of the time in debugging the programs. If he works 48 hours during the week , how many hours did he spend debugging the program.
1 4579

2 Answers on this Question

  1. Here is the ans with explanation…..
    Just divide 48 hours into 8 parts…
    for flowchart its 1/4 so it is 2/8 = 12hours
    For Coding it is 3/8 = 18 hours
    the rest is again 3/8 = 18 hours for debugging..

Leave a Reply

Your email address will not be published. Required fields are marked *

Scroll to top