if 30 men completes a job in 15 days working 9 hrs per day.. how much hours per day should 40 men work ??

if 30 men completes a job in 15 days working 9 hrs per day.. how much hours per day should  40 men work ??

Ques:- if 30 men completes a job in 15 days working 9 hrs per day.. how much hours per day should 40 men work ??
2 9603

2 Answers on this Question

  1. as i assume the time taken to complete the job is not to be
    changed while increasing the employees as it does not
    clearly states so……….
    30 men wrk for 9 hrs
    therefore for the work to be done if no of workers is
    increases the no of hrs / day to work should decrease so
    here s a inverse relation
    solving further we get
    30 = K /9 ==> K= 270
    now
    40 = 270/y ==> y= 6.75
    therefore ans is d)none

  2. convert days in hours so 15*9=135 hours
    30 men complete a job in = 135 hours
    time for 1 man to complete the same job = 135*30
    time for 40 men to do the same job = 135*30/40
    so the answer will be 6.75 that is (d) none