To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
The technical storage or access that is used exclusively for statistical purposes.
The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
as i assume the time taken to complete the job is not to be
changed while increasing the employees as it does not
clearly states so……….
30 men wrk for 9 hrs
therefore for the work to be done if no of workers is
increases the no of hrs / day to work should decrease so
here s a inverse relation
solving further we get
30 = K /9 ==> K= 270
now
40 = 270/y ==> y= 6.75
therefore ans is d)none
convert days in hours so 15*9=135 hours
30 men complete a job in = 135 hours
time for 1 man to complete the same job = 135*30
time for 40 men to do the same job = 135*30/40
so the answer will be 6.75 that is (d) none