as i assume the time taken to complete the job is not to be
changed while increasing the employees as it does not
clearly states so……….
30 men wrk for 9 hrs
therefore for the work to be done if no of workers is
increases the no of hrs / day to work should decrease so
here s a inverse relation
solving further we get
30 = K /9 ==> K= 270
now
40 = 270/y ==> y= 6.75
therefore ans is d)none
convert days in hours so 15*9=135 hours
30 men complete a job in = 135 hours
time for 1 man to complete the same job = 135*30
time for 40 men to do the same job = 135*30/40
so the answer will be 6.75 that is (d) none
We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By clicking “Accept”, you consent to the use of ALL the cookies.
This website uses cookies to improve your experience while you navigate through the website. Out of these cookies, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may have an effect on your browsing experience.
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.
as i assume the time taken to complete the job is not to be
changed while increasing the employees as it does not
clearly states so……….
30 men wrk for 9 hrs
therefore for the work to be done if no of workers is
increases the no of hrs / day to work should decrease so
here s a inverse relation
solving further we get
30 = K /9 ==> K= 270
now
40 = 270/y ==> y= 6.75
therefore ans is d)none
convert days in hours so 15*9=135 hours
30 men complete a job in = 135 hours
time for 1 man to complete the same job = 135*30
time for 40 men to do the same job = 135*30/40
so the answer will be 6.75 that is (d) none