P and Q together can do a work in 6 days. If P alone can do it in 15 days. In how many days can Q alone do it?

P and Q together can do a work in 6 days. If P alone can do it in 15 days. In how many days can Q alone do it?

Ques:- P and Q together can do a work in 6 days. If P alone can do it in 15 days. In how many days can Q alone do it?
2 9094

2 Answers on this Question

  1. (Q+R) 6 days work

    = 7×6=42 Units

    then in 3 days = total work = 18

    P Completes = 60−42=18 units .

    P’s eff. 183 = 6 units/day

    Q’s eff= 10−6=4 units/day

    R’s eff = 7−4=3 units/day

    P completes whole work in =606 = 10 days

    R completes whole work in =603= 20 days

    diff , is20−10=10 days

  2. Assume Q can do the work alone in Q days:

    work of a day by both P and Q =>
    (1/15) + (1/Q ) = 1/6
    solving this Q = 10.