This is Expert Verified Answer 22 people found it helpful author link Lipimishra2 Expert 568 answers 113.9K people helped Let the no. of men (originally) be x. x no. of men require 10 days. if however there were 10 men less it will take 10 days more for the work to be finished. ——> means x-10 men require 10+10=20 days. 10x = 20 (x-10) x = 2x -20 => x = 20. Reply
This is Expert Verified Answer
22 people found it helpful
author link
Lipimishra2
Expert
568 answers
113.9K people helped
Let the no. of men (originally) be x.
x no. of men require 10 days.
if however there were 10 men less it will take 10 days more for the work to be finished. ——> means x-10 men require 10+10=20 days.
10x = 20 (x-10)
x = 2x -20 => x = 20.