5 men or 8 women do equal amount of work in a day. a job requires 3 men and 5 women to finish the job in 10 days how many woman are required to finish the job in 14 days.
Lets assume total LCM(5,8) = 40units.
As, 5 men or 8 women do equal amount of work in a day,
1 Man does 8units/day and 1 Woman does 5units/day.
3M and 5W in 10 days do (3*8 + 5*5)*10 = 490units
To do 490 units in 14 days, number of Women required = 490/(14*5) = 7