  1. 8men = 6days
    8 men do 1/6 th work in 1 day
    so 1 man does 1/8 * 1/6 work =1/48 work in 1 day
    in 1/2 day he does 1/96 th work
    To complete the work (1) in 1/2 day requires 96 men
    So answer is 96

  2. 8men=6days
    Let X be the no.of mens required to complete work in 1/2 day
    Xmen=1/2days
    m1=8,d1=6
    m2=X,d2=1/2
    Formula:m1*d1=m2*d2
    8*6=X*(1/2)
    X=8*6*2
    X=96
    Answer=96