A certain number of men can finish a piece of work in 10 days. If however there were 10 men less it will take 10 days more for the work to be finished. How many men were there originally?

A certain number of men can finish a piece of work in 10 days. If however there were 10 men less it will take 10 days more for the work to be finished. How many men were there originally?

Ques:- A certain number of men can finish a piece of work in 10 days. If however there were 10 men less it will take 10 days more for the work to be finished. How many men were there originally?
1 2381

One Answer on this Question

  1. This is Expert Verified Answer
    22 people found it helpful
    author link
    Lipimishra2

    Expert
    568 answers
    113.9K people helped

    Let the no. of men (originally) be x.
    x no. of men require 10 days.

    if however there were 10 men less it will take 10 days more for the work to be finished. ——> means x-10 men require 10+10=20 days.

    10x = 20 (x-10)
    x = 2x -20 => x = 20.