Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men work to complete the job?

Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men work to complete the job?

Ques:- Thirty men take 20 days to complete a job working 9 hours a day. How many hour a day should 40 men work to complete the job?
A. 8 hrs
B. 7 1/2 hrs
C. 7 hrs
D. 9 hrs

5 6825

5 Answers on this Question

  1. (30Men x 20days x 9hrs)/(40Men) = 135 hrs per day. Which
    is impossible. So, the answer is none.
    Since the question is vague, if you don’t answer this
    question you may be given mark for this question.
    The question should have been
    1. How many days 40 men working 9 hrs a day will take to
    complete the work.
    Answer: (30Men x 20days x 9hrs)/(40Men x 9 hrs) = 15days
    2. How many hours a day should 40 men work for 20days will
    take to complete the work.
    Answer: (30hrs x 20day x 9hrs)/(40Men x 20days)=6 3/4 hrs

  2. ans : (b)
    30 mem in 180hrs in 20 days
    efficiency of each person is 1/180*30
    efficiency of 40 mem is 40/180*30 = 1/45*3
    no.of hrs per day = 45*3/20 = 7.22 hrs (app)